HALLEN FOOTBALL CLUB,
BRISTOL
Hallen Football Club's project involved the refurbishment and extension of an existing MUGA, to create a new 3G pitch. The original size of the court was 1,800 square meters, before Sportfields' converted the area to a total of 2,592m2. With the help of funding from Facilitating Sport, along with capital raised by the club internally through various events, all parties worked together on budget to deliver a facility that would benefit the club and the local community long into the future. Sportfields delivered the project ahead of schedule so that a handover from a very special guest was achieved. We were privileged when Ex-pro, England legend John Barnes, cut the ribbon to unveil the new floodlit, third-generation football pitch.
​
Works carried out;
Cutting back all bushes, brambles and vegetation
Taking down existing fencing
Power cleaning of the existing surface, restoring porosity by introducing gravel filled holes through the macadam layer
Excavation to allow for extension of court
Concrete kerb installation
Type 3 stone sub-base
In-situ SBR shock-pad
Desso 40mm pile height carpet complete with blue & white play lines for football
3 Metre high twin wire fencing, incorporating 1.2m super rebound panel system surrounding perimeter of court
Single & Double gate installation to match fencing
Upgrading of current floodlighting system
​
​
​
Contract Value: £150,000.00