ST MARY'S AND ST GILES PRIMARY SCHOOL,
MILTON KEYNES
It was a pleasure to work with Jeakins Weir for the installation of a TigerTurf multi-sport system at Stony Stratford, Milton Keynes. This particular scheme posed a great challenge due to the means of access to site. Careful manoeuvring around the back of the school, due to narrow bends, was required from delivery vehicles to eliminate any risk of accident occurring. This was managed effectively by several banks men to assist both drivers and any members of the public walking nearby. An aluminium trackway was installed to keep the surrounding areas in good condition.
​
Total size of pitch installed;
75m x 48m plus 2x goal recesses (7m x 2m) = 3,628m2
​
Works undertaken;
Topsoil Strip
Cut & Fill works
Drainage system at 5m centres, including carrier drain and connections to outfall
Geotextile membrane
Type 3 Sub Base
Concrete Kerbing
40mm depth of 20mm open grade porous tarmac to ATP area
15mm Insitu rubber E-layer shockpad
Tiger Turf Evo Pro 18mm Pile Height – Sand Dressed
Multi-sport line markings for Football, Netball and Tennis
3m High Zaun Duo8 perimeter fencing with gates
Shaping of surrounding banks
Independent testing of surface
​
Contract Value: £280,000.00